The Mandeville City Council recently approved a change order for a net increase of $52,940 on its 2004-05 Street Improvement Program.
Jimmy Ray, an engineer and architect with Meyer Engineering, said the changes are because some projects were added and others removed. He added that a time extension is needed for the Villere Street drainage project.
|
|
The original contract price was $1,246,500 but would go up to $1,405,830 once the change orders were approved.
It listed its change order justifications as:
In a letter dated March 21 from Rick Meyer, owner of Meyer Engineers of Metairie, he recommended the net increase and 28-day time extension.